From mid-November through December 2025, Lindmore’s maintenance staff completed a substantial number of projects on the docket for its 2025-2026 winter maintenance schedule. However, due to increased rain in mid-December that caused Millerton’s storage to fill up, Lindmore and its Friant partners prepared to receive water from the reservoir at the direction of the U.S. Bureau of Reclamation, who monitors Millerton’s storage.

Lindmore prides itself on being prepared and ready to adapt to changing hydrologic conditions and system demands, while also progressing through its slated winter maintenance program. Lindmore plans for events like this during its annual maintenance schedule to be ready to accommodate storage releases.

An updated progress report for maintenance is below.

2025-2026 Winter Maintenance Progress Update

Line Replacement
40%
Main Line Leak Repair
67%
Air Vent Repair / Replacements
43%
Moss Pit Maintenance
100%
Pump Station Maintenance
93%
1st Ave Meter & Valves
53%
5th Ave Meter & Valves
33%
10th Ave Meter & Valves
50%