Lindmore Irrigation District Project Portfolio Helps Move the Needle on Groundwater Sustainability
News
December 10, 2025

Groundwater recharge projects are an important component of reaching groundwater sustainability under the Sustainable Groundwater Management Act (SGMA). Without groundwater recharge, the region experiences reduced water availability long-term, risks to groundwater quality, and sinking land due to groundwater overdraft.
Alongside delivering water to growers, Lindmore Irrigation District is also responsible for collaborating to make groundwater levels sustainable under SGMA. By recharging the aquifer during wet years, Lindmore can be part of the solution, managing groundwater effectively and reducing the burden on landowners during dry years. Learn more about each project below.

Mariposa

Mariposa is a joint effort among the City of Lindsay, Department of Water Resources, and Lindmore Irrigation District. The project was funded by a Prop 68 Grant and Lindmore ID and put into service in 2023. The facility sits on the south side of Mariposa Street, just east of Highway 65. Mariposa has a sustained inflow rate of 10 acre-feet a day.

Hirabayashi

Put into service in 2017, Hirabayashi is located at the corner of Ave 208 and M Avenue. Hirabayashi is approximately 25 acres and consists of three separate recharge basins. Hirabayashi has a sustained inflow rate of 15 acre-feet per day.

5th Avenue

Put into service in 2023, 5th Avenue is located on Road 188, divided by Avenue 208. The 320-acre facility consists of four recharge ponds on the south side of Avenue 208, and a release valve on the north side. 5th Avenue has a sustained inflow rate of 100 acre-feet a day.

1st Avenue

1st Avenue is on the northeast corner of Avenue 224 and Road 188. The project is approximately 150 acres, consisting of 35-acre ponds, and 70 acres of overflow space. The facility was put into service in 2024 and has a sustained inflow rate of 70 acre-feet per day.

Lewis Creek

A joint effort between Lindmore Irrigation District and the Department of Water Resources, Lewis Creek added a siphon from the Friant-Kern canal into the natural channel of Lewis Creek. Put into service in 2025, Lewis Creek has a maximum inflow rate of 100 acre-feet per day, and a sustained inflow rate of 40 acre-feet per day.